How To Install Gas Boiler Combustion System
2016-06-28 17:42:07 From:ZBG

Gas Steam Boiler Combustion system is one of the most important boiler systems in a boiler. Knowing how to install the combustion system is very important. 

wns gas steam boiler.jpg

1. The installation of oil pipes or gas pipes should be accord to the design of boiler room.
2. Hydrostatical test is made and Hydraulic test pressure is 1.25 times than work pressure, when fuel system is finished (The minimum test pressure is 0.4MPa).
3. When fuel system piping is installed completely, they should be washed by water or steam more than twice until clean medium is removed. When washing, you should have some technical measures approved. After washing, you should remove dead angle and residue.
4. When fuel system piping is installed completely, Oil circulation test is made to the total system.
5. Gas should be sent to the burner to the shortest way. The diameter of air duct must be larger than the fittings pipe.
6. Gas-tight test is made when fuel system piping is installed completely. Gas-tight test is made to fittings parts with more than 1bar air or inert gas firstly. Total test is made to all pipe system from main cut off device to cut off valve of burner with air or inert gas (1.1*work pressure and the minimum pressure is 50mbar) at the condition of electromagnetic valve closed. Region connection is painted with foam material or anti-corrosion materials.

Recommendation
  • Effective Ways to Improve Chain Grate Boiler 2021-08-26
  • Problems in the Operation of Chain Grate Boilers 2021-08-26
  • Low-speed Circulating Fluidized Bed Boilers 2021-08-25
  • Auxiliary Equipment for Coal-Fired Power Plant Boilers 2021-08-25
  • Get A Free Quote

    Please fill in the form below to send us a brief message, and we will get back to you as soon as possible.

    Name: E-mail: Your Needs: Other Demand: